North Wind's Weir Duwamish Salmon Habitat Acquisition and Restoration Project

On February 6, 125 volunteers continued transforming the project site by planting hundreds of 600 trees and shrubs and 900 willow/dogwood stakes. Photos of the event will be posted here by close of business Monday, February 8.

Volunteer Opportunities at North Wind's Weir on February 27 and in April.

General project questions: Dennis Clark, 206-296-1909.

Construction Concluded December 18

Construction finished on December 18 and inspection took place December 21.

On December 17, KING 5's Gary Chittim reported on the North Wind's Weir estuary restoration project. View the KING 5 news story on North Wind's Weir restoration.

Aerial photos from December 18 of the nearly-completed project.

Photo of people in hard hats and vests standing on a river bank
The photo above shows staff from the U.S. Army Corps of Engineers, King County, and the construction contractor inspecting the North Wind's Weir estuary restoration project on December 21.

Photo of shoreline covered in beauty bark
The photo above shows the compeleted project on December 21, looking east. The upper limit of tidal action coincides with the lower boundary of the brown beauty bark. The beauty bark suppresses weeds and reduces erosion. The tree trunks chained to anchors will provide shelter for young fish during high tide.

Photo of riverbank covered with beauty bark
The photo above looks west across the project site on December 21. The area covered in beauty bark will be planted with trees and shrubs in February.

Photo of riverbank covered in beauty bark
The photo above shows the northern portion of the project at the conclusion of construction on December 21. The "trees" installed vertically are perching trees that also will provide a habitat for cavity-dwelling birds such as woodpeckers.

Aerial photo of large embayment on a river
The photo above provides an aerial view of the North Wind's Weir estuary restoration during the morning of December 18. At low tide, the project will be nearly completely drained. Photo by Ned Ahrens, King County.

Photo of large embayment on a river bank
A second view of the project on the morning of December 18. Coincidentally, these aerial photos were taken not long after the following two photos. Photo by Ned Ahrens, King County.

Photo of embayment along a river
The photo above shows the North Wind's Weir restoration project on the morning of December 18. Most of the mudflat habitat that is most beneficial to young salmon is underwater in this picture. Beauty bark is being blown down to stabilize the soil and suppress weeds. Photo courtesy of Norbert Woloszyn.

Photo of river embankment with beauty bark along the shoreline
The photo above shows the North Wind's Weir restoration project on the morning of December 18. The beauty bark is placed above the high tide line. The area covered in beauty bark will be planted with trees and shrubs in February 2010. The area between the lower limit of the beauty bark and the water's edge will be planted with marsh plants in April 2010. Contact Dennis Clark to sign up for notices of the volunteer planting events. Photo courtesy of Norbert Woloszyn.

Photo of embayment next to river
The photo above shows the site on December 16. The chain link fence along S. 112th St. in the foreground has been removed and the split rail fence is under construction. The yellow material around the east and north edges of the excavated area is coir fabric, a coconut-based fabric used to stabilize the soil. This will be covered with beauty bark by the end of the week. Photo courtesy of Norbert Woloszyn.

As of December 15, the earthmoving was nearly entirely completed at the North Wind's Weir estuary restoration project. Tidal cycles were filling and draining the site as intended.

Photo of open water next to graded bank with tree trunks lying on it
The photo above shows the project on December 15 during an 8 foot tide (5.7 feet on site plans). The traverse berm that formerly ran left to right in the middle of the excavated area has been completely removed. Tree trunks ("large wood") have been placed in their final locations and anchored in place.

Photo of large embayment next to a river with gentle muddy banks and tree trunks scattered around
The photo above looks west through the opening to the Duwamish River on December 15. The yellow boom is the float for the silt curtain intended to minimize the spread of turbidity from the project area to the river.

Photo of embayment next to a river with gentle muddy banks with tree trunks scattered on them
This December 15 view looks southwest along the eastern edge of the project. The black object in the lower left is a culvert for stormwater from a neighboring property. The culvert has a Tideflex duckbill check valve to keep tidewater from backing up to the neighboring property. The white material on the quarry spall below the culvert is ice from the previous week's cold weather.

Photo of tree stuck in bank next to large embayment on a river
This final December 15 view looks southwest across the majority of the site. The tree is a snag that has been placed to provide perching habitat for birds.

As of December 9, the project looked like this:

Photo of large embayment on a river
The photo above shows the project on December 9. Ice is floating in the middle of the excavated area and has accumulated around the edges. Even though this part of the river is tidally influenced, fresh water -- which freezes more easily than salt water -- sits on top of the salt water that fills most of the site. Three snag trees can be seen at the right and upper parts of the site. Photo courtesy of Norbert Woloszyn.

By the morning of December 7, further excavation had left the site looking like this:

Photo of wide stretch of a river with construction equipment on the bank
The photo above shows the site on the morning of December 7. The northern berm is out of view under water, having been graded to its final elevation. Photo courtesy of Norbert Woloszyn.

Photo of river with construction equipment on the shoreline
The photo above also was taken on the morning of December 7. Although not quite complete, the project now is functionally part of the Duwamish estuary. Photo courtesy of Norbert Woloszyn.

Later in the day, the following photos were taken:

Photo of man standing by excavated muddy area
The photo above looks northeast across the site at low tide in the afternoon of December 7. The material in front of the man will be excavated. The darker material that looks like "ring around the bathtub" shows the extent of high tide in the site to date.

Photo of open water surrounded by mud
This photo looks west across the site to the entrance to the Duwamish during low tide on December 7. The log at left has been driven into the ground to serve as a snag for birds and insects.

On December 4, tidal waters of the Duwamish River completely filled the excavated area of the estuary restoration for the the first time as is shown in the two photos below.

Photo of excavated area filled with water next to river
The photo above shows the southern cell during the morning of December 4. Earlier in the morning, tidewaters covered the berm on the right. The ultimate main entrance to the river -- which will allow the site to drain completely at low tide -- still remains to be dug. Photo courtesy of Norbert Woloszyn.

Photo of excavated area filled with water next to a river
The photo above shows the central temporary berm between the southern (left) and northern (right) cells on the morning of December 4. The morning high tide covered the central berm and although the tide is going out in this photo, still covers the berm between the northern cell and the river. Photo courtesy of Norbert Woloszyn.

The December 4 milestone of first complete tidal innundation was reached during the final earthmoving phase of the project which began three days prior. Beginning in the evening of December 1, crews began the final phase of earthmoving to open up the project site to the Duwamish River. At 10 p.m. on December 1, a small group of Boeing employees (who work across the street) and project supporters went on a tour of the site to see the work kick off. They walked through a surreal landscape as construction equipment roared and rolled across the site under bright construction lights.

During the following days, work occurred both during the day and at night during low tides to allow equipment to work in the dry. Earthmoving should be completed during the second week of December.

Volunteer plantings of trees, shrubs, and wetland plants will occur in February and April 2010.

Photos of people in vests and hard hats standing in muddy construction site next to a river
The photo above shows the project team and contractor meeting on December 1 to assess progress. At this meeting, they decided to go ahead with the final grading work during the low tides and dry weather of this week.

Photo of construction equipment and logs on bank above a muddy pond
The photo above shows construction on the morning of December 2. The trackhoe is moving the logs to place them in clusters, where they will provide shelter for fish.

Photo of trackhoe reaching down earthen bank next to a river
The photo above shows a trackhoe making final contours to the bank of the Duwamish. The area where the photographer is standing had been further excavated overnight. In a day or two, high tides should begin overtopping this location.

Construction Progresses During November 2009

Photo of construction area next to a river with water in large ponds surrounded by construction equipment
The photo above shows the site on November 25. The majority of the grading is complete and large wood is being placed on the slopes. Compare this view to a photo of the same location taken two weeks prior. Photo courtesy of Norbert Woloszyn.

Photo of excavator placing a log on a slope above a pond
This photo shows workers securing large wood pieces together in the area that eventually will be subject to tides and changes in river elevation. The wood will provide shelter for young salmon. Photo courtesy of Norbert Woloszyn.

The following photos were taken on November 11. Water in the excavated areas is a mix of stormwater, water from a broken water pipe (now fixed), and seepage through the sandy soil from the high water table. Water is pumped from one pond to the other to give crews space to work.

Photo of excavated area next to a river
View on November 11 looking north toward the project site from the Boeing Customer Services Building located south of S. 112th St. Compare this view to a photo of the same location taken one week prior. Photo courtesy of Norbert Woloszyn.

Photo of construction site with water in pond
View looking northwest across the site on November 11. The Duwamish River is beyond the construction equipment. Pump in the foreground is used to shift water between the ponds as needed. Photo courtesy of Norbert Woloszyn.

Construction Half Way Done in Early November 2009

By early November, the excavation and grading were about half done. The following seven photos were taken on November 4.

Photo of bulldozer grading a bare slope
A bulldozer grades the eastern slope of the site. Tree trunks piled up in far distance eventually will be placed in the large open area to provide refuge habitat for young salmon.

Photo of bulldozer grading a slope with more construction equipment in the distance
This photo looks southwest. The eventual opening to the Duwamish River will be located between the construction trailers and the excavator on top of the bank in the center distance of the photo.

Photo of large excavated pit with construction equipment in the distance
This photo looks south and shows the north-south extent of the project. Water in the bottom is from seepage. The open area will be further deepened in the next two weeks before an opening is excavated to the Duwamish.

Photo of excavator placing soil in dump truck
Approximately every 10 minutes, a dump truck enters the site and is loaded with excavated soil. This soil will be used where clean fill is required.

Photo of pit with construction equipment in it
This photo looks northeast across the extent of the site. The eventual opening to the Duwamish will be located between the photographer's location and the trackhoe on the far left. Note that some large pieces of wood already have been placed on the southern slope at right.

Photo of river bank with construction equipment on top of the bank

This photo looks south (upstream) on the Duwamish River. Contaminated soil from this stretch of the river bank was removed during the winter of 2009. Compare this November 4 view to a picture taken at this location in February.

Photo looking down on a construction site next to a river
View on November 4 looking north toward the project site from the Boeing Customer Services Building located south of S. 112th St. Photo courtesy of Norbert Woloszyn.

Construction Began in Early October

The contractor began work at the beginning of October.

July 28, 2009 Groundbreaking

A celebratory groundbreaking for the final, main construction phase of the North Wind's Weir estuarine restoration project occurred July 28, 2009.

Download the program for the groundbreaking (Adobe Acrobat).

Photo of man speaking with river in background
Tukwila Mayor Jim Haggerton welcomed people to the site for the July 28 groundbreaking.

Man standing at podium with river in the background
State representative Zack Hudgins, whose district includes the project site, spoke about the various ways Washington State is helping local partners recover the Duwamish River and Puget Sound.

Picture of line of people in hard hats shoveling dirt
Representatives of the many organizations that contributed to the North Wind's Weir estuary restoration project helped with the ceremonial groundbreaking.

Photo of people standing next to a box sitting in a hole in the ground
Those breaking ground found "buried treasure": a box containing chocolate salmon symbolic of the rewards to come when the site is providing habitat for millions of young salmon.

February-April 2009 Soil Cleanup

 

Photo of lattice-like dam structure next to river
In 2008, most of the remaining contaminated soil was removed from the site. To remove the last remaining contaminated soil in the riverbank itself, it was necessary to construct a temporary barrier. This photo shows the "Portadam" being assembled in February 2009.

Photo of dam-like structure parallel to river bank
This photo shows how the "Portadam" sits right at the edge of the river at low tide. At high tide, river flow backs up enough to cover the rocks in the foreground and much of the Portadam. February 2009 photo.

Photo of lattice-like structure covered in blue tarps next to a river
This view, looking upstream, shows the "Portadam" in action, holding back the river water and allowing excavation work to continue. Pumps are used to remove water that seeps around the Portadam. February 2009 photo.

Photo of beach along river
This March 2009 photo shows the site after the remaining contaminated soil and Portadam have been removed.

Photo of river bank
This April 2009 photo looking downstream shows the new northern berm constructed during the removal of the last contaminated soil earlier in 2009. Coir fabric and straw are used to reduced erosion. The patch of green on the mudflat is emergent marsh vegetation.

Photo of riverbank
This April 2009 photo looks upstream during low tide. The straw-covered area is part of the newly-constructed northern berm. The eventual connection between the off-channel, shallow water habitat project and the river will occur upstream of the rocky promontory at the end of the straw-covered berm.

Photo of barren field next to river
View looking toward project site on April 20, 2009, from roof of Boeing Customer Services Building located south of S. 112th St. Photo courtesy of Norbert Woloszyn.

2008 Soil Cleanup

Photo of large excavated area
The majority of the contaminated soil was removed in 2008. Contamination consisted mostly of oil-soaked soil from previous industrial uses of the property. In addition, there were large (refrigerator-sized) chunks of concrete that had been buried on site. May 2008 photo.

Project Details

Download a vicinity map (Adobe Acrobat).

North Wind's Weir Estuarine Habitat Project Plans (Adobe Acrobat 3.7 MB)

North Wind's Weir Estuarine Habitat Project topography and vegetation design
(Adobe Acrobat 469 KB)

To learn more, contact Dennis Clark, 206-296-1909.

Project Description

Partners and Funding

Aerial photo of Site 1 Duwamish project areaImportance for Salmon

Other Watershed Salmon Restoration/Protection Projects

Volunteer Opportunities at North Wind's Weir in 2010

This project needs your help! Volunteers will help plant trees, shrubs, and wetland plants in 2010. They also will construct fences to keep geese away from the newly-planted wetland plants.

People of all ages and experience levels are welcome with the exception of the April 3 event, which is for adults and teens only.

Date and Time Name More information and sign up
Saturday, February 27
10 a.m. -
2 p.m.

North Wind's Weir Restoration Planting
We will continue the work of planting trees and shrubs begun February 6. Enjoy planting in the sandy, rock- and root-free soil. This will be the easiest planting experience you've ever had!

Information for volunteers from People For Puget Sound.

Dhira Brown, People For Puget Sound,
206-382-7007 Ext. 182

Saturday, April 3
10 a.m. -
2 p.m.
North Wind's Weir Restoration Goose Exclusion Fence Construction
Geese like nothing better than the tender marsh plants we are planting at the project. To foil these aquatic grazers, we will construct a fence around the areas we will plant with the marsh plants on April 17. No experience necessary to help with this unusual restoration task! However, you will get muddy -- wear rubber boots and pants/jacket that you don't mind getting dirty. Adult and teenaged volunteers only for this event, please.

Dhira Brown, People For Puget Sound,
206-382-7007 Ext. 182

Saturday, April 17
10 a.m. -
2 p.m.

North Wind's Weir Restoration Planting
Plant wetland plants in the intertidal zone. Also help complete construction of a goose-exclusion fence to protect the young plants. You will get muddy -- wear rubber boots and pants/jacket that you don't mind getting dirty.

This is a Duwamish Alive! event, one of a series of projects up and down the Duwamish in Seattle and Tukwila on this day.

Dhira Brown, People For Puget Sound,
206-382-7007 Ext. 182

Saturday, June 19
10 a.m. -
2 p.m.
North Wind's Weir Restoration Stewardship
At this event, we'll do any final restoration work required. Work is likely to consist of light weeding (there are almost no weeds on site now).

Dhira Brown, People For Puget Sound,
206-382-7007 Ext. 182

Volunteer opportunities for other dates and at other locations in southern King County